Construction of the Coastal Port
ˇˇˇˇSummary
As for the construction of the coastal ports in 1994, 37.27 billion RMB was invested, 125.1 percent of the year plan. The Ministry of Communication centralized the arrangement for the investment of 32. 07 billion RMB (including Tianjin port, Yantian port of Shenzhen City). 17 large- & medium-sized projects of coastal ports were arranged (including 14 projects provided directly by the Ministry of Communication and 3 projects arranged by local provinces, cities of Autonomous Regions) and 34.76 billion RMB was invested. 1994 witnessed the completion of 8 key projects, 81 berths, of which composed 20 deep water berths, 21 medium-sized berths and 40 small-sized berths, which increased the throughout capacity of 2.854 million tons. In 1995, 11 large- & medium-sized projects of coastal ports in the transportation system were completed, among which are 10 key construction projects. 12 deep water berths were established (excluding Tianjin port, Yantian port of Shenzhen city, Xiamen port), which increased the throughout capacity of 4,700,000 tons and roll-on-roll-off vehicles to 190,000. By the end of 1995, the deep water berths in the coastal ports in transportation system (including the number of berth down from the Nanjing Yantze River) had been reached 412 and the total throughout capacity designed reached 7.117 billion tons. |
ˇˇ
Table 7 The Deep Water Berths at the Ports Completed & Went into
Operation in Transportation System between 1993-1995.
Year |
Item name |
Deepwater berth (number) |
Scale and function |
Handing capacity (10 000t) |
1993 |
The coal berth-the 1st phase of the front-bay project, Qingdao port. | 2 |
50,000-tonnage and 35,000-tonnage coal berth each | 1 500 |
| The bulk grain berth-2nd phase of the Miaoling project, Lianyungang port; | 1 |
35,000-tonnage bulk grain berth | 200 |
|
| Commonly-used berth-2nd phase of Langshan port, Nantong port. | 2 |
13,000-tonnage commonly used berth. | 150 |
|
| West part of 2nd phase of Zhangjiagang port | 3 |
25,000-tonnage wood berth, 20,000 tonnage coal berth and 10,000-tonnnage general cargo berth each |
550 |
|
| Bulk grain berth of Bingding wharf, Qinghuangdao port | 1 |
35,000-tonnage bulk grain berth | 170 |
|
| Newly-established east pier project (north side), Tianjin port. | 6 |
two 10,000-tonnage iron & steel berths, four 10,000 tonnage general cargo berths |
198 |
|
| 2nd phase project of Jinzhou port | 1 |
10,000-tonnage general cargo berth |
30 |
|
1994 |
1st phase of Waigaoqiao project of Shanghai port | 4 |
25,000-tonnage container berth, 15,000-tonnage multipurpose berth; 25,000-tonnage wood berth, 15,000-tonnage mineral berth. |
240 |
| 35,000-tonnage coal berth, Shantou port coal berth | 1 |
35,000-tonnage coal berth, Shantou port coal berth | 410 |
|
| 5 berths in front of Xinshagang port, Guangzhou port | 5 |
20,000-30,000 tonnage coal berth, coal ( mineral ) multipurpose berth general cargo berth, bulk chemistry berth. |
910 |
|
| 2nd phase of south of no.1 region, Zhanjiang port | 5 |
10,000-20,000 tonnage non-metalic mineral berth, iron & steel berth, general cargo berth, container berth and wood berth each |
200 |
|
| 2nd phase of Dadong port project, Dandong port. | 3 |
10,000-tonnage general cargo berth. | 95 |
|
| 20,000-tonnage general cargo berth, Tangshan port | 1 |
20,000-tonnage general cargo berth | 90 |
|
| Xiuyu general cargo berth of Meizhou bay, Fujian province. | 1 |
10,000-tonnage general cargo berth. | 35 |
|
| 2nd phase of Dongdu project, Xiamen port | 4 |
35,000-tonnage container berth, 25,000 tonnage coal berth, two 20,000-tonnage general cargo berths |
350 |
|
| Coal wharf of Macun port, Hainan province | 1 |
35,000-tonnage coal wharf | 90 |
|
| Gaolan port | 2 |
two 20,000-tonnage general cargo berths | 250 |
|
1995 |
2nd phase of Rizhao port project | 5 |
10,000-tonnage and 15,000-tonnage general cargo berth each; 10,000-tonnaget and 15,000-tonnage bulk cargo berth each. 15,000-tonnage general cargo & container berth concurrently. | 200 |
| 1st phase of Xugou port area project, Lianyungang port | 2 |
two 15,000-tonnage general cargo berths | 70 |
|
| 1st phase of deep water region project, Shantou port | 2 |
two 15,000-tonnage multipurpose berth and 15,000-tonnage general cargo berth each | 120 |
|
| 2nd phase of Langshan port area project, Nantong port | 1 |
25,000-tonnage container berth |
5 |
|
| Roll-in-roll-off wharf by truck, Yingkou port | 1 |
10,000-tonnage roll-in-roll-off berth | 19 |
|
| 10,000-tonnage multipurpose berth, south area of Weihai port | 1 |
10,000-tonnage multipurpose berth | 40 |